Project Name:Truewind (6414)

Location:Huntington Beach, CA

Type:Residential

Contract Value:$ 1.7 MM

Project Summary:

Wet utility pipeline installation onsite and offsite for new homes.

Highlights:

Sewer Off Site Public - installing 6" and 8" sewer pipeline laterals, 48" manholes with POLY Lining, asphalt removal and temp hot patch on Pioneer

Sewer On Site Private - installing over 1,600 LF of 8" PVC, 48" sewer manholes with poly lining, sewer cleanouts, sewer laterals, and a sewer lift station.

Water Off and On Site Public - installing over 1,600 LF of 8" PVC water main pipeline, gate vales, fire hydrants, blow offs, tees and bends with cathodic protection and thrust blocks, 8" ductile iron pipe CL 350, and water service hot taps for over 40 water service installations, irrigation water services, 6" PVC water main, and also includes removal of asphalt and placement of hot patch and permanent patch work.

Storm Drain Off Site Public - installing over 1,200 LF of rubber-gasket 24", 30", 36" and 42" reinforced concrete pipe, catch basins, junction structures, and bulkhead. Also includes removal of asphalt and placement of hot patch and permanent patch

Storm Drain On Site Private - installing over 1,400 LF of 18", 36" and 48" rubber gasket reinforced concrete pipe, over 700 LF of 4" - 8" PVC and fittings, junction structures, Orifice Plate, Storm Drain Pump Station, concrete inlet, bio-retention facility, rip rap, perforated pipeline, and a Contech ® CDS unit.

Sewer and Water Park Site - over 500 LF of pipeline and 48" sewer manhole

Storm Drain Park Site - over 500 LF of 18" and 24" rubber gasket reinforced concrete pipe, water quality curb inlet, junction structures, NDS Atrium grates, and concrete inlets.