Project Summary:

Kana coordinated with other MEP trades to validate that the intricate wet and dry pipeline framework proposed to build this new school would not conflict with the actual underground wet utility pipeline installation for sewer, domestic water, fireline, and various other drainage pipelines.

Highlights: Installed over 4,000 LF of 6", 4" and 2" VCP Sewer Pipe, cleanouts, manholes, multiple connections to existing sewer main in street ROW, lunch shelter drains, over 10,000 LF of combined 60", 24", 18", 15", 12", 10", 8", 6" 4" and 3" HDPE storm drainage pipe, flap gate valve, 1,800 LF of perforated footing drain, catch basins, local depressions, catch basins abandonments and removals, approximately 700 LF of 24" and 18" RCP storm drain line, planter drains, concrete and asphalt restoration; Contech Storm Water Treatment Vortsentry Units; over 3,500 LF of 6" and 8" PVC domestic and fire water main, RPPD assemblies and backflows, fire hydrants, hot taps, and fire department connections.

HDPE Installation.jpgSewer Trench.jpg

Tags: , , , , , , , , , , , ,

| Print Print