Project Name:2011 Retail Zone Phase 2 (5308)

Location:Orange, CA

Type:Public Works

Client:East Orange County Water District

Contract Value:$275,625.00

Project Summary:

The East Orange County Water District (EOCWD) Board of Directors awarded the 2011 Distribution System Improvements, Phase 2 portion, to Kana Pipeline at their June 16th meeting.

Highlights:

Kana Pipeline's scope includes approximately 1,500 LF of 8" PVC DR25 (or DIP CL350 pipe TBD), pipeline abandonments, connections to existing pipeline, 30+ water services, new fire hydrants, and a fire hydrant reconnect, gate valves, airvac assemblies, blow-off assemblies, and over 15,000 sq ft of pavement restoration on Fairhaven, Barrett Lane, Carmel and Maynard.

Additional scope of work also includes survey staking, verification of utilities, traffic control, record drawings (as-builts), O&M Manuals, warranties and excavation safety measures.